考虑模具约束和工装生产的铸造车间作业计划联合方法

劳嘉良 ,  胡常伟 ,  赵翼翔

工业工程 ›› 2026, Vol. 29 ›› Issue (3) : 134 -145.

PDF (1099KB)
工业工程 ›› 2026, Vol. 29 ›› Issue (3) : 134 -145. DOI: 10.3969/j.issn.1007-7375.240362
生产调度与系统优化

考虑模具约束和工装生产的铸造车间作业计划联合方法

作者信息 +

Joint Scheduling of Casting Workshops Considering Mold Constraints and Tooling Production

Author information +
文章历史 +
PDF (1124K)

摘要

在家居企业铸造车间中,砂芯加工和浇铸加工是铸造工艺的关键环节。二者相互关联,砂芯加工需要在浇铸之前完成,而浇铸又依赖于前期砂芯的加工进度。在实际生产中,由于二者作业计划不协调,一方的延误会直接影响到另一方的进度,从而导致整个订单的拖期,同时生产过程还存在模具约束。基于以上问题,本文构建了以最小化订单总拖期时间为目标的联合调度优化模型,旨在通过改进灰狼优化算法解决铸造车间中的作业调度问题,并提出一种基于知识的进化搜索算子以增强全局搜索能力,提升求解的精度和效率。基于由企业实际订单及工艺结构生成的多个基准算例,结合正交试验法进行参数优化。实验结果表明,所提改进算法在求解效率和优化质量上优于传统的调度算法;在减少订单拖期时间方面,改进算法相较于对比算法具有显著的优势,且在实际生产中的应用效果良好,能够有效减少作业过程中的不确定性,提高生产调度的精度和灵活性。

Abstract

In the foundry workshop of a home furnishing enterprise, sand core manufacturing and casting are two key operations with strong interdependence and precedence constraints: sand core manufacturing must be completed before casting, while casting depends on the progress of upstream sand core production. In actual production, poor coordination between these two production schedules often causes delays in one stage to propagate to the other, resulting in overall order tardiness. In addition, mold constraints in the production process further increase scheduling complexity. To address these issues, this paper constructs a joint scheduling optimization model with the objective of minimizing total order tardiness. An improved grey wolf optimization algorithm is proposed to solve the job scheduling problem in casting workshops, and a knowledge-based evolutionary search operator is introduced to enhance the global search capability and improve solution accuracy and efficiency. Multiple benchmark instances generated from practical orders and process structures are used to optimize the parameters through orthogonal experiments. Experimental results show that the proposed algorithm is superior to traditional scheduling algorithms in both solution efficiency and optimization quality. The improved algorithm significantly outperforms the benchmark algorithm in reducing order tardiness and performs well in practical production, effectively reducing operational uncertainty and improving the accuracy and flexibility of production scheduling.

关键词

作业计划联合 / 模具约束 / 组装约束 / 知识 / 灰狼优化算法 (GWO)

Key words

joint scheduling / mold constraint / assembly constraint / knowledge / grey wolf optimization algorithm (GWO)

引用本文

引用格式 ▾
劳嘉良,胡常伟,赵翼翔. 考虑模具约束和工装生产的铸造车间作业计划联合方法[J]. 工业工程, 2026, 29(3): 134-145 DOI:10.3969/j.issn.1007-7375.240362

登录浏览全文

4963

注册一个新账户 忘记密码

参考文献

[1]

唐红涛, 杨志鹏, 刘家毅. 考虑工序并行的差异工件批调度研究[J]. 工业工程, 2021, 24(3): 68-76.

[2]

Tang Hongtao, Yang Zhipeng, Liu Jiayi. A research on batch scheduling with non-identical job sizes considering parallel processes[J]. Industrial Engineering Journal, 2021, 24(3): 68-76.

[3]

Stawowy A, Duda J. Coordinated production planning and scheduling problem in a foundry[J]. Archives of Foundry Engineering, 2017, 17(3): 133-138.

[4]

Li X X, Guo X, Tang H T, et al. An improved cuckoo search algorithm for the hybrid flow-shop scheduling problem in sand casting enterprises considering batch processing[J]. Computers & Industrial Engineering, 2023, 176: 108921.

[5]

Tang H T, Fang B, Liu R, et al. A hybrid teaching and learning-based optimization algorithm for distributed sand casting job-shop scheduling problem[J]. Applied Soft Computing, 2022, 120: 108694.

[6]

严晖. 基于遗传算法的注塑成型车间生产计划优化研究——以 F 公司为例[D]. 福州: 福州大学, 2017.

[7]

胡常伟, 陈新度, 陈庆新, . 含不一致任务重量的同型熔炼炉批调度优化[J]. 工业工程, 2014, 17(3): 73-78.

[8]

Hu Changwei, Chen Xindu, Chen Qingxin, et al. Optimization for scheduling identical parallel melting furnaces with non-identical job weights[J]. Industrial Engineering Journal, 2014, 17(3): 73-78.

[9]

de Araujo S A, Arenales M N, Clark A R. Lot sizing and furnace scheduling in small foundries[J]. Computers & Operations Research, 2008, 35(3): 916-932.

[10]

Teixeira Junior R F, Fernandes F C F, Pereira N A. Binary integer programming formulations for scheduling in market-driven foundries[J]. Computers & Industrial Engineering, 2010, 59(3): 425-435.

[11]

Cowling P, Rezig W. Integration of continuous caster and hot strip mill planning for steel production[J]. Journal of Scheduling, 2000, 3(4): 185-208.

[12]

Yang J P, Liu Q, Guo W D, et al. Quantitative evaluation of multi-process collaborative operation in steelmaking-continuous casting sections[J]. International Journal of Minerals, Metallurgy and Materials, 2021, 28(8): 1353-1366.

[13]

王成尧, 高麟, 汪定伟, . 有模具约束的平行机台最小拖期和调度问题[J]. 系统工程学报, 1999, 14(4): 345-350.

[14]

Wang Chengyao, Gao Lin, Wang Dingwei, et al. Minimize total tardiness of the parallel machine with modulo constrain[J]. Journal of Systems Engineering, 1999, 14(4): 345-350.

[15]

赵海丹. 有模具限制的并行机台调度问题研究[D]. 长春: 吉林大学, 2016.

[16]

李金霖, 尹成龙. 考虑模具约束和开机成本的并行机调度问题研究[J]. 运筹与管理, 2024, 33(4): 105-111.

[17]

Li Jinlin, Yin Chenglong. Parallel machine scheduling problem considering mold constraints and machine opening cost[J]. Operations Research and Management Science, 2024, 33(4): 105-111.

[18]

张刚志, 周炳海. 带换模约束的非等效并行机作业族调度方法[J]. 计算机集成制造系统, 2013, 19(12): 3162-3169.

[19]

Zhang Gangzhi, Zhou Binghai. Job families scheduling for non-identical parallel machines with setup time constraints[J]. Computer Integrated Manufacturing Systems, 2013, 19(12): 3162-3169.

[20]

王有远, 董博文. 考虑序列相关准备时间的分布式柔性作业车间调度研究[J]. 工业工程, 2024, 27(3): 78-86.

[21]

Wang Youyuan, Dong Bowen. Distributed flexible job shop scheduling with sequence-dependent setup times[J]. Industrial Engineering Journal, 2024, 27(3): 78-86.

[22]

Mirjalili S, Mirjalili S M, Lewis A. Grey wolf optimizer[J]. Advances in Engineering Software, 2014, 69: 46-61.

[23]

Kennedy J, Eberhart R. Particle swarm optimization[C]// Proceedings of ICNN'95 - International Conference on Neural Networks. Piscataway: IEEE, 2002: 1942-1948.

[24]

罗哲, 朱光宇, 杨志锋, . 多策略相结合粒子群算法求解作业车间调度问题[J/OL]. 计算机集成制造系统, 2024: 1-24(2024-02-20). https://link.cnki.net/doi/10.13196/j.cims.2023.0611.

[25]

Luo Zhe, Zhu Guangyu, Yang Zhifeng, et al. Multiple-strategy particle swarm optimization for solving job-shop scheduling problems[J/OL]. Computer Integrated Manufacturing Systems, 2024: 1-24 (2024-02-20). https://link.cnki.net/doi/10.13196/j.cims.2023.0611.

[26]

刘建军, 李钦颂, 曾创锋, . 柔性装配流水车间调度与分批配送集成问题研究[J]. 计算机集成制造系统, 2025, 31(11): 4026-4043.

[27]

Liu Jianjun, Li Qinsong, Zeng Chuangfeng, et al. Flexible assembly flowshop scheduling with batch delivery[J]. Computer Integrated Manufacturing Systems, 2025, 31(11): 4026-4043.

[28]

Wang J J, Wang L. A knowledge-based cooperative algorithm for energy-efficient scheduling of distributed flow-shop[J]. IEEE Transactions on Systems, Man, and Cybernetics: Systems, 2020, 50(5): 1805-1819.

[29]

时维国, 宋存利. 求解混合流水车间调度问题的改进灰狼算法[J]. 计算机集成制造系统, 2021, 27(11): 3196-3208.

[30]

Shi Weiguo, Song Cunli. Improved grey wolf optimization for solving hybrid flow shop scheduling problem[J]. Computer Integrated Manufacturing Systems, 2021, 27(11): 3196-3208.

基金资助

国家自然科学基金项目(61973089)