多因素约束下金属矿深部区域 TBM 施工巷道支护方案分析——以某铜矿为例
李金哲 , 于露杨 , 孙扬 , 吴之栋
有色金属(矿山部分) ›› 2026, Vol. 78 ›› Issue (6) : 184 -190.
多因素约束下金属矿深部区域 TBM 施工巷道支护方案分析——以某铜矿为例
Analysis on support scheme of TBM constructed drifts in deep metal mine areas under multi-factor constraints:a case study of a copper mine
深部金属矿山的开采面临着三高一扰动等问题,使得深部工程巷道掘进存在巨大挑战。传统钻爆法施工具有作业不连续、人员长期暴露在工作面等缺陷,难以满足矿山建设的要求,采用隧道掘进机(TBM)进行长距离机械连续作业是深部金属矿山开挖巷道的现实趋势。本文以某国外地下铜矿为工程背景,对影响TBM 施工的主要因素进行分析,计算发现:1)根据现有矿山生产系统的通风需求,适配于斜坡道的TBM 直径为8 m,巷道净断面积为42.1 m2,适配于竖井的TBM 直径为10.6 m,巷道净断面积为78.8 m2。2)本工程预测巷道最大涌水量为240 m3/d,不会对施工造成严重影响。3)建模对比仅喷砼支护条件下的围岩变形,按照一次TBM 随机短锚杆配合100 mm 喷砼支护+ 二次TBM 主机后锚索配合100 mm 喷砼支护能够使巷道区域最大变形量降低30% 以上。研究结果能够对其它相似深部金属矿的TBM 施工支护方案选择提供依据与参考。
Deep-seated metal mining is confronted with problems such as "three highs and one disturbance",which poses great challenges to roadway excavation in deep engineering. The conventional drilling-and-blasting method suffers from discontinuous operations and long-term personnel exposure at working faces,making it difficult to meet mine construction requirements. Adopting Tunnel Boring Machine (TBM) for long-distance continuous mechanical excavation represents a practical trend for roadway construction in deep-seated metal mines.Taking an overseas underground copper mine as the engineering background,this paper analyzes the main factors affecting TBM construction. Calculation results show:1) Based on ventilation requirements of the existing mine production system,the suitable TBM diameter for ramps is 8 m with a roadway net cross-sectional area of 42.1 m2;for shafts,the suitable TBM diameter is 10.6 m with a roadway net cross-sectional area of 78.8 m2. 2) The predicted maximum water inflow of roadways for this project is 240 m3/d,which will not exert severe impacts on construction. 3) Numerical modelling comparing surrounding-rock deformation under shotcrete-only support indicates that the combined support scheme-primary support of TBM "driven random short rock bolts plus 100 mm shotcrete,followed by secondary support of anchor cables behind the TBM mainframe plus 100 mm shotcrete" can reduce the maximum deformation within the roadway zone by more than 30%. The research findings can provide basis and reference for TBM construction and support-scheme selection of other similar deep-seated metal mines.
| [1] |
蔡美峰,谭文辉,吴星辉, |
| [2] |
|
| [3] |
李广,史志远,余洪伟. 金属矿山深井大规模提升关键技术装备进展与发展趋势[J]. 矿业研究与开发,2024,44(9):1-8. |
| [4] |
|
| [5] |
徐长磊,刘育明,邓皓泽, |
| [6] |
|
| [7] |
李勇,陈虎忠,朱航宇, |
| [8] |
|
| [9] |
刘泉声,潘玉丛,余宏淦, |
| [10] |
|
| [11] |
张基伟,张佳鑫,陈弦, |
| [12] |
|
| [13] |
陈弦,刘垚,张基伟. 敞开式TBM 掘进巷道围岩稳定性分析及滞后支护方案优化[J]. 金属矿山,2026(5):90-101. |
| [14] |
|
| [15] |
孟佑强,马文著,马昊, |
| [16] |
|
| [17] |
李智,董书宁,石志远, |
| [18] |
|
| [19] |
杨延栋,赵建兵,周建军, |
| [20] |
|
| [21] |
GB 50086—2015岩土锚杆与喷射混凝土支护工程技术规范[S]. |
| [22] |
GB 50086— 2015 Technical code for engineering of ground anchoring and shotcrete support[S]. |
深地国家科技重大专项项目(2024ZD1003800)
/
| 〈 |
|
〉 |