建筑工程土建施工工艺优化与现场施工质量把控探讨

作者信息 +

Exploration on the Optimization of Civil Engineering Construction Techniques and On-Site Construction Quality Control

Author information +
文章历史 +
PDF (911K)

摘要

以某12万m2高层住宅工程为对象,针对8.5 m深基坑支护、1500 m3大体积混凝土浇筑及密集钢筋节点施工难点,开展土建施工工艺优化与质量管控研究。基坑支护采用复合土钉墙与预应力锚杆组合体系,大体积混凝土采用30 cm分层、5 m分段连续浇筑及信息化温控措施,钢筋工程应用BIM预建模与模块化绑扎方法,并构建班组自检、项目部复检、监理终检三级质量管控体系。实施结果表明,优化后施工周期由180 d缩短至150 d,质量问题发生率由8%降至3%,关键工序直接成本降低5%,复杂节点绑扎效率提高20%,混凝土内外温差稳定控制在25 °C以内。研究表明,工艺协同优化与全过程质量追溯相结合,能够有效提升高层住宅土建施工的质量稳定性、组织效率及经济效益。

Abstract

This study takes a high-rise residential construction project spanning 120,000 m2 as its case study to investigate the optimization of civil engineering construction techniques and the implementation of quality control measures, addressing the technical challenges associated with the support of an 8.5 m deep foundation pit, the pouring of large-volume concrete (1,500 m3), and the construction of dense steel reinforcement joints. For the foundation pit support, a composite system combining soil nailing walls and prestressed anchor rods was employed; for the large-volume concrete pouring, a layered pouring method with 30 cm thickness and a segmented pouring approach with 5 m intervals, along with information-based temperature control measures, was adopted; for the steel reinforcement work, BIM-based pre-modeling and a modular tying method were utilized; and a three-tiered quality control system-comprising self-inspection by work teams, re-inspection by the project department, and final inspection by the supervision unit-was established. The implementation results demonstrate that the optimized construction schedule was shortened from 180 days to 150 days, the incidence rate of quality issues was reduced from 8% to 3%, the direct cost of key construction processes was lowered by 5%, the tying efficiency for complex joints was increased by 20%, and the temperature difference between the interior and exterior of the concrete was consistently kept within ±25°C. This study indicates that combining process synergistic optimization with full-process quality traceability can effectively enhance the quality stability, organizational efficiency, and economic benefits of civil engineering works for high-rise residential buildings.

关键词

高层住宅 / 土建施工 / 深基坑支护 / 大体积混凝土 / BIM技术

Key words

high-rise residential buildings / civil engineering construction / deep foundation pit support systems / large-volume concrete / BIM technology

引用本文

引用格式 ▾
姜泽楠. 建筑工程土建施工工艺优化与现场施工质量把控探讨[J]. 工程设计与施工, 2026, 8(10): 26-28 DOI:10.12349/edc.v8i10.12077

登录浏览全文

4963

注册一个新账户 忘记密码

参考文献

[1]

王浩. 建筑工程的施工质量及安全管理工作的实践探究[J]. 城市开发, 2024,(13): 160-161.

[2]

陈格清. 装配式装饰施工技术在建筑工程中的实践与优化[J]. 中国建筑金属结构, 2025, 24(22): 79-81.

[3]

郭文玲. 土建工程预算审核方法及有效控制建筑工程结算[J]. 中国住宅设施, 2024,(12): 95-97.

[4]

陈国泉. 关于加强建筑工程质量管理的探讨[J]. 工程质量, 2024, 42(S2): 78-80+84.

AI Summary AI Mindmap
PDF (890KB)

4

访问

0

被引

详细

导航
相关文章

AI思维导图

/

〈 〉