高海拔边坡支护结构优化与施工技术研究

王治 ,  王绍健 ,  申磊 ,  潘宇 ,  王健

工程设计与施工 ›› 2026, Vol. 8 ›› Issue (10) : 32 -35.

PDF (893KB)
工程设计与施工 ›› 2026, Vol. 8 ›› Issue (10) : 32 -35. DOI: 10.12349/edc.v8i10.12079

高海拔边坡支护结构优化与施工技术研究

作者信息 +

Research on the Optimization and Construction Techniques of High-Altitude Slope Support Structures

Author information +
文章历史 +
PDF (914K)

摘要

针对马尔康党坝锂辉石矿3900~4300m高海拔边坡支护工程原“抗滑桩+后植筋桩板墙”方案存在的植筋易损伤主筋、低温下抗拔力失控、节点耐久性不足等缺陷,结合高海拔施工特点,通过工艺试验和数值模拟,提出"桩顶降标高+柱板墙顺做法"优化方案:将桩顶降至墙底标高,以整体式柱板墙替代后植筋挂板,桩筋与柱筋采用滚轧直螺纹套筒机械连接,按3m一模分阶顺作施工。工程验证表明,该方案彻底规避后植筋质量风险,整体稳定安全系数1.38,施工期最大位移仅12mm,工期缩短22%,造价降低15%,为高海拔矿山边坡支护提供了技术路径。

Abstract

For the 3900~4300m high-altitude slope support project at the Markang Dangba lithium spodumene mine, the original "anti-slide pile with post-installed rebar wall" scheme had issues like main rebar easily getting damaged during rebar installation, uncontrolled pull-out force at low temperatures, and insufficient durability at connection points. Considering the characteristics of high-altitude construction and through process testing and numerical simulation, an optimized "lower pile top height with integrated column-wall" method was proposed: the pile top is lowered to the base level of the wall, and an integrated column-wall replaces the post-installed rebar panel. The pile rebar and column rebar are mechanically connected using threaded couplers, and the construction proceeds in 3-meter sections in sequence. Engineering verification shows that this plan completely avoids the quality risks of post-installed rebar, has an overall safety factor of 1.38, a maximum displacement of only 12mm during construction, shortens the construction period by 22%, and reduces costs by 15%, providing a technical solution for high-altitude mine slope support.

关键词

抗滑桩 / 后植筋缺陷 / 柱板墙 / 顺做法施工 / 机械连接

Key words

anti-slip piles / post-installed rebar defects / column-slab walls / conventional construction / mechanical connection

引用本文

引用格式 ▾
王治,王绍健,申磊,潘宇,王健. 高海拔边坡支护结构优化与施工技术研究[J]. 工程设计与施工, 2026, 8(10): 32-35 DOI:10.12349/edc.v8i10.12079

登录浏览全文

4963

注册一个新账户 忘记密码

参考文献

[1]

GB 50330-2013, 建筑边坡工程技术规范[S]. 北京: 中国建筑工业出版社, 2013.

[2]

JGJ 107-2016, 钢筋机械连接技术规程[S]. 北京: 中国建筑工业出版社, 2016.

[3]

李海光, 周勇. 桩板墙不同类型挂板的技术经济比较[J]. 中国地质灾害与防治学报, 2025, 36(3): 78-85.

[4]

张伟, 李明. 高海拔地区建筑施工技术难点及应对策略[J]. 建筑技术, 2025, 56(12): 1456-1460.

[5]

王建国, 刘畅. 抗滑桩结构损伤及补强技术应用研究进展[J]. 岩土工程技术, 2026, 40(1): 1-8.

[6]

赵明华, 陈刚. 高海拔寒冷地区混凝土施工关键技术研究[J]. 施工技术, 2025, 54(8): 89-93.

AI Summary AI Mindmap
PDF (893KB)

4

访问

0

被引

详细

导航
相关文章

AI思维导图

/

〈 〉