廊坊某污水处理厂扩建工程设计
Design of Expansion Project for a Wastewater Treatment Plant in Langfang
为响应环保政策升级与区域污水处理负荷增长需求,廊坊开发区第二污水处理厂实施提标扩容工程,总投资25,000万元。厂内处理规模4万m³/d,厂外配套8万m³/d泵站(服务一厂、二厂),采用“预处理+改良Bardenpho生物处理+高效沉淀池+V型滤池+超滤+次氯酸钠消毒”组合工艺,针对性解决原有工艺污染物去除短板。运行结果显示,出水CODCr≤30mg/L、BOD5≤6mg/L、TP≤0.3mg/L等指标连续半年稳定达《北京市地方标准-城镇污水处理厂水污染物排放标准》(DB11/890-2012)B标准,部分出水可中水回用,为京津冀区域同类提标扩容工程提供实践参考。
To address the requirements of upgraded environmental protection policies and the growing regional wastewater treatment load, the Langfang Development Zone No.2 Wastewater Treatment Plant implemented an upgrading and capacity expansion project with a total investment of 250 million yuan. The on-site treatment capacity is 40,000 m³/d, and the supporting off-site pump station is designed for 80,000 m³/d (serving both the No.1 and No.2 Plants). A combined process of “pretreatment + modified Bardenpho biological treatment + high-efficiency sedimentation tank + V-type filter + ultrafiltration + sodium hypochlorite disinfection” was adopted to specifically address the shortcomings of the original process in pollutant removal. Operational results indicate that key effluent indicators, including CODCr ≤ 30 mg/L, BOD5 ≤ 6 mg/L, and TP ≤ 0.3 mg/L, have stably met the Class B requirements specified in the Beijing Local Standard - Discharge Standard of Water Pollutants for Municipal Wastewater Treatment Plants (DB11/890-2012) for six consecutive months. A portion of the effluent can be reused as reclaimed water, providing practical reference for similar upgrading and capacity expansion projects in the Beijing-Tianjin-Hebei region.
| [1] |
姚伟涛, 肖社明, 张永祥。 改良Bardenpho工艺处理低BOD5/TN混合污水工程设计[J]. 中国给水排水, 2025, 41(20): 68-73. |
| [2] |
颉亚玮, 朱方俊, 冯伟华, |
| [3] |
KaykhaiiS. Enhancingstorm water treatment throug hultrafiltration: Impact of cleaning chemical sand back wash durationonmembrane efficiency[J]. Water Science & Technology, 2023, 88(12): 3893-3905.(DOI: 10.2166/wst.2023.453) |
/
| 〈 |
|
〉 |