浅谈山岭隧道穿越管道安装优化设计探究
On the Optimization Design of Pipeline Installation in Mountain Tunnel Crossings
随着我国经济与科学技术的不断发展,大口径天然气长输管道在焊接技术、施工工艺、机械化程度等方面得到迅速发展,但目前山岭隧道使用的断面尺寸及管道布置只能基本满足隧道内手工焊及半自动焊管道安装施工的空间需求,但在全自动焊、材料运输、逃生通道空间等方面受限,造成工效较低,本文综合分析了山岭隧道断面尺寸及隧道内管道安装布置的现状,通过分析,提出了山岭隧道内管道安装布置优化设计的必要性,进一步探讨了天然气长输管道穿越山岭隧道内管道安装布置优化设计方向。
With the continuous development of China’s economy and science and technology, large-diameter natural gas long-distance pipelines have achieved rapid progress in welding techniques, construction processes, and mechanization levels. However, the cross-sectional dimensions and pipeline layouts currently used in mountainous tunnels can only meet the basic spatial requirements for manual and semi-automatic welding pipeline installation within tunnels, while being constrained in terms of fully automated welding, material transportation, and emergency evacuation space, resulting in lower work efficiency. This paper comprehensively analyzes the current status of cross-sectional dimensions and pipeline installation layouts in mountainous tunnels. Through analysis, it highlights the necessity for optimized design of pipeline installation layouts in mountainous tunnels and further explores the direction for optimizing the pipeline installation layout of long-distance natural gas pipelines traversing mountainous tunnels.
/
| 〈 |
|
〉 |