摘要
基坑工程和建筑地基基础施工在城市地下空间开发和高层建筑建设中互相联系,二者在时间、空间以及力学行为上相互影响,从而决定整个工程的安全性和经济性。本文从协同施工的工程意义入手,对基坑开挖和地基基础施工之间相互制约的关系进行了系统地分析,提出了以变形协调、时序优化、信息反馈为特征的协同施工技术体系,并就土方开挖与桩基施工协同、内支撑与筏板浇筑协同、降水与地基加固协同这三种典型的应用场景进行了详细地论述。经研究得知,创建基坑同地基基础一体化的施工组织和过程控制手段,可以明显减少相邻工序间的不利干扰,改善资源利用情况以及结构整体稳定状况。
Abstract
Foundation pit engineering and building foundation construction are interconnected in urban underground space development and high-rise building construction. They mutually influence each other in terms of time, space, and mechanical behavior, thereby determining the safety and economy of the entire project. This article starts with the engineering significance of collaborative construction, systematically analyzes the mutually restrictive relationship between foundation pit excavation and foundation construction, proposes a collaborative construction technology system characterized by deformation coordination, time sequence optimization, and information feedback, and discusses in detail three typical application scenarios: the collaboration between earth excavation and pile foundation construction, the collaboration between internal support and raft slab pouring, and the collaboration between dewatering and foundation reinforcement. Research has shown that creating an integrated construction organization and process control method for foundation pits and foundations can significantly reduce adverse interference between adjacent processes, improve resource utilization, and enhance the overall stability of the structure.
关键词
Key words
[Author(id=1330198339899708039, tenantId=1045748351789510663, journalId=1327662952484470822, articleId=1330198339052458612, orderNo=0, firstName=null, middleName=null, lastName=null, nameCn=null, orcid=null, stid=null, country=null, authorPic=null, dead=0, email=null, emailSecond=null, emailThird=null, correspondingAuthor=0, authorType=1, ext={EN=AuthorExt(id=1330198339958428297, tenantId=1045748351789510663, journalId=1327662952484470822, articleId=1330198339052458612, authorId=1330198339899708039, language=EN, stringName=Yingjun Liu, firstName=Yingjun, middleName=null, lastName=Liu, prefix=null, suffix=null, authorComment=null, nameInitials=null, affiliation=null, department=null, xref=null, address=Middling Coal Jiangnan Construction Development Group Co., Ltd., Guangzhou, Guangdong, 510080, China, bio=null, bioImg=null, bioContent=null, aboutCorrespAuthor=null), CN=AuthorExt(id=1330198340000371338, tenantId=1045748351789510663, journalId=1327662952484470822, articleId=1330198339052458612, authorId=1330198339899708039, language=CN, stringName=刘英俊, firstName=null, middleName=null, lastName=null, prefix=null, suffix=null, authorComment=null, nameInitials=null, affiliation=null, department=null, xref=null, address=中煤江南建设发展集团有限公司, 中国·广东 广州 510080, bio={"content":"刘英俊(1988-),男,中国河南信阳人,本科,工程师,从事地基与基础研究。
"}, bioImg=null, bioContent=刘英俊(1988-),男,中国河南信阳人,本科,工程师,从事地基与基础研究。
, aboutCorrespAuthor=null)}, companyList=[AuthorCompany(id=1330198339828404867, tenantId=1045748351789510663, journalId=1327662952484470822, articleId=1330198339052458612, xref=null, ext=[AuthorCompanyExt(id=1330198339840987780, tenantId=1045748351789510663, journalId=1327662952484470822, articleId=1330198339052458612, companyId=1330198339828404867, language=EN, country=null, province=null, city=null, postcode=null, companyName=null, departmentName=null, remark=Middling Coal Jiangnan Construction Development Group Co., Ltd., Guangzhou, Guangdong, 510080, China), AuthorCompanyExt(id=1330198339853570693, tenantId=1045748351789510663, journalId=1327662952484470822, articleId=1330198339052458612, companyId=1330198339828404867, language=CN, country=null, province=null, city=null, postcode=null, companyName=null, departmentName=null, remark=中煤江南建设发展集团有限公司, 中国·广东 广州 510080)])])]
刘英俊.
基坑工程与建筑地基基础协同施工技术研究[J].
工程设计与施工, 2026, 8(7): 4-6 DOI:10.12349/edc.v8i7.11031
| [1] |
朱余佳. 软土地区深基坑开挖对临近既有建筑物的影响[J]. 武夷学院学报, 2025, 44(09): 18-23.
|
| [2] |
范金刚. 邻近浅基础公共建筑深基坑工程安全风险管理研究[D]. 湖南大学, 2024.
|
| [3] |
蔡忠祥, 岳建勇, 张凯, 等. 软土地基文物建筑正下方基坑支护设计与实践[J]. 地下空间与工程学报, 2023, 19(S1): 235-244.
|