双护筒隔离减阻钻孔灌注桩施工技术研究
Research on the Construction Technology of Double Casing Isolation and Drag-Reducing Drilled Piles
为获得不同开发阶段配建共构工程中的基桩设计参数,以实际工程为背景提出了采用双层钢护筒消除桩顶设计标高以上空桩段影响的施工措施。首先设计了超长双护筒技术参数,并采用整体吊装的方式依次安设了外层护筒和内护筒,且针对超长双护筒隔离减阻的关键在于内外护筒间隙的密封处理,提出了底端增加活动环形阻隔板+顶端密封环形板的最优改良方案。现场开挖揭示内外护筒间隔离效果良好,且试桩结果满足设计要求,表明双护筒的设置很好地消除了空桩段未开挖土层的侧摩阻力,值得进一步推广应用。
To obtain the design parameters for foundation piles in co-constructed projects at different development stages, this paper, based on an actual engineering project, proposes a construction method using a double-layer steel casing to eliminate the effect of hollow pile sections above the pile top design level. First, the technical parameters for the extra-long double casing were designed, and the outer and inner casings were installed sequentially using an overall hoisting method. The key to reducing resistance with the extra-long double casing lies in sealing the gap between the inner and outer casings. An optimal improvement plan was proposed, which includes adding a movable annular barrier plate at the bottom and a sealed annular plate at the top. On-site excavation showed that the isolation effect between the inner and outer casings was good, and the test pile results met the design requirements, indicating that the double casing setup effectively eliminated the side friction of the unexcavated soil in the hollow pile section and is worthy of further application.
| [1] |
王炎, 黄皓斌, 张浩强, |
| [2] |
童心, 黄凯, 李波, |
| [3] |
程敏, 田涌泉, 赵永军, |
/
| 〈 |
|
〉 |