煤化工EPC项目采购进度控制关键节点与管理策略

马蕴霞 ,  季旭 ,  王靖凯

科技创新与工程 ›› 2026, Vol. 3 ›› Issue (2) : 41 -43.

PDF (1045KB)
科技创新与工程 ›› 2026, Vol. 3 ›› Issue (2) : 41 -43. DOI: 10.12349/tie.v3i2.9150

煤化工EPC项目采购进度控制关键节点与管理策略

作者信息 +

Key Nodes and Management Strategies of Procurement Schedule Control for EPC Project of Coal Chemical Industry

Author information +
文章历史 +
PDF (1069K)

摘要

煤化工EPC项目装置规模大、专业接口多,关键设备与特材长周期明显,采购进度一旦偏离,往往会把设计出图、施工组织与试车投产同步拖慢。本文以总承包商采购管理视角,结合中国煤制烯烃、气化及公辅系统的常见供货结构,梳理招标订货、制造检验、运输到场与开箱移交等环节中最易失控的节点链条,并归纳现场可执行的判定口径与责任界面。研究认为,采购进度控制应以里程碑可核对、供方动作可量化、接口条件可验收为原则,形成贯穿全周期的节点清单。相关做法有助于降低到货不成套与临建返工风险,支撑项目按期投产。

Abstract

Coal chemical EPC projects involve large-scale facilities with numerous professional interfaces, and critical equipment and special materials often have long lead times. Any deviation in procurement progress can significantly delay the synchronization of design drawings, construction organization, and commissioning. From the perspective of the general contractor’s procurement management, this paper combines the common supply structures of China’s coal-to-olefins, gasification, and public auxiliary systems to identify the most vulnerable nodes in the bidding, manufacturing inspection, transportation, and unpacking and handover processes. It also summarizes the executable criteria and responsibility interfaces for on-site implementation. The study suggests that procurement progress control should adhere to the principles of verifiable milestones, quantifiable supplier actions, and inspectable interface conditions, forming a node list that spans the entire lifecycle. These practices help reduce risks of incomplete deliveries and temporary construction rework, ensuring timely project commissioning.

关键词

煤化工EPC项目 / 采购进度控制 / 关键节点 / 管理策略

Key words

coal chemical EPC project / procurement schedule control / key milestones / management strategies

引用本文

引用格式 ▾
马蕴霞,季旭,王靖凯. 煤化工EPC项目采购进度控制关键节点与管理策略[J]. 科技创新与工程, 2026, 3(2): 41-43 DOI:10.12349/tie.v3i2.9150

登录浏览全文

4963

注册一个新账户 忘记密码

参考文献

[1]

王家柳. 煤化工项目EPC总承包管理的实践研究[J]. 中文科技期刊数据库(全文版)工程技术, 2020(12):2.

[2]

强宇. EPC总承包模式下煤化工项目合同管理存在的问题及措施探讨[J]. 企业改革与管理, 2021(24):2.

[3]

刘雄杰, 王佳佳. EPC总承包企业外协外购产品质量管理方法的探索和实践[J]. 物流技术, 2020, 39(10):4.

[4]

高少卿. 煤化工采购合规管理与供应链韧性构建研究[J]. 中国化工贸易, 2025(30):16-18.

[5]

葛庆瑞. 试析大型煤化工项目物资采购管理策略[J]. 石油石化物资采购, 2023(14):10-12.

AI Summary AI Mindmap
PDF (1045KB)

0

访问

0

被引

详细

导航
相关文章

AI思维导图

/